Power Architect load calculator
Racks and kW per rack in; IT load, facility demand and a kVA planning basis out. Every assumption is on the page, and the export is ready for your engineer.
Planning basis
- IT load, kW
- 26,800
- Facility demand, kW
- 33,500
- Operating, kVA
- 35,263
- Planning basis, kVA
- 42,316
- Current at 34.5 kV MV, A
- 708.1
- Current at 138 kV HV, A
- 177.0
Every export is stamped preliminary, lists each input with where it came from (your entry or a site default), and carries the open items below. No equipment rating is selected. "Send to an RFQ" attaches this result to the RFQ form; nothing is sent until you submit it there.
The math, all of it
- IT load = racks × kW per rack + other IT load
- Facility demand = IT load × PUE
- Operating kVA = facility demand ÷ power factor
- Planning basis = operating kVA × (1 + growth allowance)
- Current = planning kVA ÷ (√3 × kV), at the MV distribution and the utility HV voltage
PUE already covers cooling and other facility overhead. Do not add mechanical load again under other IT load. PUE is an average: peak demand on a hot day can be higher, and that needs its own study.
- Available fault current from the utility. No interrupting rating is chosen here.
- Transformer count, sizing, connection, impedance and protection.
- Redundancy: N, N+1 or 2N changes installed capacity, not the load.
- Peak cooling, transient and power-quality loads beyond the PUE average.
- Utility transmission voltage (69 to 345 kV), interconnection agreement and the ownership boundary at the main transformer.
- Protective device coordination, arc-flash and short-circuit studies by the engineer of record.
Preliminary planning only. Not for construction, equipment selection or engineering approval. Final design rests with the engineer of record.
Have the number? Get the equipment.
Send the planning basis with your RFQ, or call and we will take it from there.